Inspection process for machinery, equipment, and technological lines in investment projects
Table Of Contents
Table Of Contents
As of February 15, 2024, machinery, equipment, and technological lines used in investment projects must comply with the provisions of Decision No. 29/2023/QĐ-TTg. In particular, inspection is a mandatory procedure for investment projects that use outdated technologies, pose potential environmental pollution risks, are resource-intensive, or when requesting an extension of operations in Vietnam.
To help businesses understand the implementation process, required documentation, and how to choose the right designated organization, Vinacontrol provides the detailed guide below.

Inspection process for machinery, equipment, and technological lines in investment projects
CONTENTS:
| 1. Scope and subjects required to undergo inspection under Decision 29/2023/QĐ-TTg 2. Documentation for determining the technology of the investment project 3. Inspection procedure for machinery, equipment, and technological lines in investment projects 4. Selecting a designated inspection organization |
1. Scope and subjects required to undergo inspection under Decision 29/2023/QĐ-TTg
Businesses must carry out inspection of machinery, equipment, and technological lines in the following cases:
-
Investment projects that use outdated technologies, pose potential risks of environmental pollution, or are resource-intensive (as stipulated in Points a and b, Clause 11, Article 27 of Decree No. 31/2021/NĐ-CP);
-
Investment projects requesting an extension of operational time in Vietnam.
2. Documentation for determining the technology of the investment project
According to Article 4 of Decision 29/2023/QĐ-TTg, businesses requesting to determine the technology of their investment projects must prepare the following documents:
-
Written request for technology determination, using Form No. 01 attached to the Appendix of Decision 29/2023/QĐ-TTg;
-
Description of the current technology used in the investment project, prepared using Form No. 02;
-
Valid inspection certificate for machinery, equipment, and technological lines used in the project, clearly presenting all contents as specified in Form No. 03.
→ See more: What is the inspection of machinery, equipment, and technological lines in investment projects?
3. Inspection procedure for machinery, equipment, and technological lines in investment projects
To complete the documentation for determining the technology of the investment project, businesses must carry out the inspection process as follows:
-
Initial consultation and document submission: The enterprise and Vinacontrol meet to discuss initial information and provide necessary documents and certificates according to the required checklist.
-
Site survey and development of inspection plan: Vinacontrol reviews the documents and conducts an overall survey of the project to propose a suitable inspection plan.
-
Quotation and contract signing: Upon agreement on the plan, Vinacontrol sends a service quotation and signs the inspection contract with the business.
-
On-site inspection: Vinacontrol's appointed inspectors will visit the project site to inspect the machinery, equipment, and technological lines.
-
Issuance of inspection certificate: The inspection results are recorded in an inspection certificate using the prescribed format, serving as part of the documentation for technology determination.

Inspection procedure for machinery, equipment, and technological lines by Vinacontrol
→ See more: Certification of conformity for machinery and equipment | Fast-track procedure
4. Selecting a designated inspection organization
The inspection of machinery, equipment, and technological lines in investment projects must be conducted by an organization designated by the Ministry of Science and Technology. Choosing a reputable inspection organization ensures legal compliance, reduces processing time, optimizes costs, and increases the chances of approval for technology determination documents.
Vinacontrol is proud to be a designated inspection organization by the Ministry of Science and Technology for inspecting machinery, equipment, and technological lines in investment projects under Decision No. 29/2023/QĐ-TTg. Vinacontrol is committed to providing accurate, objective inspection services and supporting businesses in complying fully with all legal regulations.

Vinacontrol – Designated by the Ministry of Science and Technology to conduct inspections for machinery, equipment, and technological lines in investment projects
→ See more: Designation decision by the Ministry of Science and Technology
Why Choose Vinacontrol?
✔️ Over 67 years of experience in inspection and conformity assessment
✔️ Expert team of professionals and inspectors with in-depth expertise and hands-on experience
✔️ Quality management system compliant with TCVN/ISO 17020 standards
✔️ State-of-the-art equipment that meets both technical and legal requirements
✔️ Inspection procedures and methods appraised and approved by the Ministry of Science and Technology
✔️ Nationwide branch network providing prompt support to clients
✔️ In-depth technical consulting, accompanying businesses through all procedures with government agencies
For any service inquiries, please contact Vinacontrol via Hotline/Zalo: 0243 943 3840 for the best consultation and support!
VI
EN